Infrastructure Work Continues for Ide School

Infrastructure Work Continues for Ide School
Posted on 06/07/2018
 

Even though the expanded sewer lines and improved drainage of the playground blacktop may not be the most exciting part of the construction and renovations at Ide School, they are much needed. 
  
This week’s images of the progress include the extensive work being completed underground, as well as the steel covering for the north addition, the steel framework for the new pick-up/drop-off canopy, and resurfacing of the blacktop playground.


With the students now on summer break, a portion of the work is now moving to the inside of the building.  Over the next two months crews will be connecting an upgraded electrical service, installing new internet fiber lines, and reinforcing steel beams throughout the school to prepare for the new roof next summer!